Sidekick Orchestration
A worked example

From a site meeting to the client update and the next steps

The homeowners’ three requests become two change orders and one honest answer about a date. The mudroom bench misunderstanding surfaces now, on paper, rather than at drywall.

Fictional custom-home builder, one project manager, eight homes a yearFictional recordsClient update you can read in fullNo client claim
Records in · finished work out

4 records.
4 automatic steps.
One human check.

What goes in

The records the workflow reads

4 ordinary records, nothing prepared specially for AI. Every fact in the finished work traces back to one of them.

N1 · Site meeting notes

Tuesday site walk with the homeowners

  • Framing complete; windows arrive next Thursday. The homeowners asked to move the kitchen island 40 cm toward the dining room and add a pot filler.
  • They noticed the mudroom bench is not on the current drawings and believe it was agreed in March.
  • Electrical rough-in walkthrough set for the following Monday at 10; they want the electrician there.
  • They asked whether the September 30 drywall date still holds.
S1 · Schedule and budget summary

Where the project stands

  • Drywall scheduled September 30, dependent on inspections passing the week before. Contingency used to date: 38 percent, mostly on the foundation drainage change.
  • Kitchen island plumbing rough-in is booked for next week; a pot filler needs a water line the plumber has not priced.
D1 · Open decisions list

Decisions and change orders

  • Change order 04 (mudroom bench): drafted in March, never signed. Not in the current drawings or the price.
  • Change order 05 (island move): not yet raised. Any island move after plumbing rough-in costs more.
  • Client has approved all lighting selections; tile selections are due Friday.
T1 · Client update template

How we write to homeowners

  • Sections: this week, next two weeks, decisions we need from you, changes and money, questions you asked. Plain words, no promises the trades have not confirmed.
  • Every change goes on a signed change order before the work is done. Dates are “planned” until the inspection that gates them has passed.

How the work runs

From records to a review-ready result

Set up once: the update template, the tone rules and the change-order rule live in one saved project. After each site walk the notes, the schedule summary and the decisions list go in; the update and the change-order drafts come out for the project manager to check.

A saved project is a folder inside your AI tool that keeps its instructions and reference files between conversations, so nothing is re-explained.

  1. The notes are read against the schedule and the decisions list

    Each homeowner request is matched to what the drawings, the price and the schedule currently say.

  2. Requests become change orders or answers

    The island move and the pot filler become change order 05; the mudroom bench is traced to unsigned change order 04; the drywall date is answered as planned, not promised.

  3. Timing is checked against the trades

    The island decision must land before the plumber’s rough-in next week, so it goes at the top of the update. The project manager sets the exact day.

  4. The update is written in the template

    This week, next two weeks, decisions needed, changes and money, questions asked. The tone rules keep out promises the trades have not made.

  5. A person reads, corrects and acts

    The project manager prices the pot filler with the plumber, confirms the wording on the bench and sends the update.

What comes out

The finished artifact

This is the full review copy. Read it the way the owner would, with the records above open beside it.

Client updateFictional · prepared for review
Review copy

Prepared for review · fictional records

After Tuesday’s site walk

Prepared for
Project manager, before sending
Built from
N1, S1, D1, T1
Status
Draft · two change orders attached
Decision needed first
Island move, before next week’s plumbing

This week and the next two

Framing is complete. Windows arrive next Thursday. The electrical rough-in walkthrough is the following Monday at 10; we are asking the electrician to attend, as you requested, and will confirm. Plumbing rough-in for the kitchen is booked for next week, which is why the island decision below comes first.

Drywall is planned for September 30. It depends on the inspections due the week before passing; we will confirm the date once they pass, not before.

Decisions we need from you

DecisionWhy nowBy
Island move (40 cm toward dining) and pot filler: sign change order 05Plumbing rough-in is booked for next week; moving the island after that costs moreBefore the plumbing rough-in; the project manager confirms the day
Mudroom bench: confirm you want it, then sign change order 04It was drafted in March but never signed, so it is not in the drawings or the priceBefore drywall; the project manager confirms the day
Tile selectionsOrdering lead timeFriday, as planned

Changes and money

Change order 05 covers the island move and the pot filler. The pot filler needs a new water line the plumber has not priced yet; the project manager will add the figure before you sign. Change order 04, the mudroom bench, is attached as drafted in March for your review. Contingency used to date is 38 percent, most of it on the foundation drainage change.

Questions you asked

  • Is September 30 still the drywall date? It is the planned date. It holds if the inspections due the week before pass; we will confirm it once they do.
  • Was the mudroom bench agreed? A change order was drafted in March but never signed, so it never reached the drawings or the price. Change order 04 puts that right if you want the bench.

Cover message · draft for approval

To
The homeowners
Subject
Your site-walk update, and one decision before the plumbing rough-in
Attach
Change orders 04 and 05

Thanks for walking the site with us on Tuesday. The update is attached. One decision needs you before the plumber roughs in the kitchen next week: the island move and pot filler. The project manager will confirm the exact day with you. The mudroom bench question is answered inside, and both change orders are attached for your review.

Human review

What the owner checks before it goes out

The drywall date is planned, not confirmed. Framing is complete, not inspected; the electrician is asked, not booked. No decision deadline is invented. The pot filler has no price until the plumber gives one. The bench is a question, not an accusation. Every change goes on a change order before work. Nothing is sent until the project manager has read it.

Try it

Run the same records through your own AI tool

The complete fictional pack and the instruction are below. Paste both into an AI chat you are allowed to use, then compare what comes back with the brief above.

Copy this fictional example

Copy the notes and instructions into an approved AI chat.

Fictional source material: N1 · TUESDAY SITE WALK WITH THE HOMEOWNERS Framing complete; windows arrive next Thursday. The homeowners asked to move the kitchen island 40 cm toward the dining room and add a pot filler. They noticed the mudroom bench is not on the current drawings and believe it was agreed in March. Electrical rough-in walkthrough set for the following Monday at 10; they want the electrician there. They asked whether the September 30 drywall date still holds. S1 · WHERE THE PROJECT STANDS Drywall scheduled September 30, dependent on inspections passing the week before. Contingency used to date: 38 percent, mostly on the foundation drainage change. Kitchen island plumbing rough-in is booked for next week; a pot filler needs a water line the plumber has not priced. D1 · DECISIONS AND CHANGE ORDERS Change order 04 (mudroom bench): drafted in March, never signed. Not in the current drawings or the price. Change order 05 (island move): not yet raised. Any island move after plumbing rough-in costs more. Client has approved all lighting selections; tile selections are due Friday. T1 · HOW WE WRITE TO HOMEOWNERS Sections: this week, next two weeks, decisions we need from you, changes and money, questions you asked. Plain words, no promises the trades have not confirmed. Every change goes on a signed change order before the work is done. Dates are “planned” until the inspection that gates them has passed.
Your task: Prepare the client update from Tuesday’s site walk, the schedule and budget summary and the decisions list, in our template. Answer their questions honestly, turn their requests into the change orders they need, and list what we need from them and by when. Do not confirm the drywall date or price the pot filler; those are the project manager’s calls.

Check the result

The drywall date is planned, not confirmed. Framing is complete, not inspected; the electrician is asked, not booked. No decision deadline is invented. The pot filler has no price until the plumber gives one. The bench is a question, not an accusation. Every change goes on a change order before work. Nothing is sent until the project manager has read it.

Apply it to your work

Before trying this on your firm's real files, use a business AI account and make sure someone checks every result before it is used.

Try your last site meeting: the notes, your schedule summary, your open decisions and your template. Judge the update by whether it caught the request that would have become a change order at drywall.