Prepared for review · fictional records
Next week · two crews, five customers, two owner decisions
- Prepared for
- Owner and office, Thursday
- Built from
- J1, C1, S1, R1
- Status
- Proposed · nothing confirmed
- Owner decisions
- Clinic overtime; solar slip plan
The plan, as it fits the rules
| Day | Crew A (Marco, Dev) | Crew B (Sam, Nia) |
|---|
| Monday | Solar day 1 with Crew B, once panels are on site (by 9 am) | Solar day 1 with Crew A |
| Tuesday | Solar day 2 (lift on site) | Solar day 2 with Crew A |
| Wednesday | Open, in case solar runs over (lift still rented) | Van 2 in for brakes; rides with Crew A if needed |
| Thursday | EV charger, first home, from 8 am | Inverter callback from 8 am; clinic upgrade from 6 pm if overtime is approved |
| Friday | EV charger, second home, from 8 am | Sam only; owner names who meets the inspector at 9 am |
The two clashes, and the decisions they need
- The panels arrive Monday between 7 and 9 am, so an 8 am start cannot be guaranteed [S1, R1]. Proposed: tell the customer the crew arrives between 9 and 11 am, once the panels are on site. The lift is rented through Wednesday [C1], and Wednesday is kept open, so a one-day slip is covered.
- If the solar install runs past Wednesday, the lift rental ends and Crew A is booked for the first EV charger on Thursday. Owner decision now: extend the lift rental by a day, or move that EV charger with the customer’s agreement [C1, R1].
- The clinic upgrade must be finished before the inspector sees it on Friday at 9 am, and it can only happen after hours [J1]. Thursday from 6 pm is the latest slot before the inspection; it needs the owner’s overtime approval [C1, R1]. If overtime is declined, the inspection has to be rebooked with the inspector before the clinic is told anything else.
What the rules kept out
- No booked customer day moved. The solar customer gets a later arrival window on the booked day, not a different day.
- The inspection stays Friday at 9 am, after the upgrade it has to check.
- The callback takes the first slot after its part arrives. The EV chargers, whose customers are flexible, fit around it and around the solar job.
- Saturday was not used: it falls after the Friday inspection.
- Each EV charger has its own day, so a half-day job that starts late cannot push the next one into overtime.
Customer confirmations · drafts for approval
- To
- Five customers, one message each
- Send by
- Thursday of this week, per our rule
Solar customer: Your install stays on Monday and Tuesday. Your panels arrive Monday morning, so the crew will arrive between 9 and 11 am, once the panels are on site, rather than at 8.
Clinic (only if the owner approves overtime): We plan to complete the panel upgrade on Thursday evening, starting at 6 pm after you close, so it is finished before the inspector’s visit on Friday at 9 am. Please confirm Thursday evening works.
EV charger, first home: Thursday, arrival window 8 to 10 am.
EV charger, second home: Friday, arrival window 8 to 10 am.
Inverter callback: Thursday, arrival window 8 to 10 am. The replacement part arrives the day before.